March 2006
 |
|
Permanent
Creek Golf Cart Bridge
The Permanent Creek Golf Cart Bridge was delivered to Shoreline on Thursday, February 23
and set in place on Friday February 24th. The project is expected to be completed in
March. |
Shoreline Sailing Lake
Water Supply Project
You may be wondering what is happening on the north shore of the Shoreline Sailing
Lake
Water from San Francisco Bay Estuarys Outer Charleston Slough enters the City owned
Inner Charleston Slough daily through tidal action. Large tide gates installed by the City
several years ago help regulate the flow and prevent flooding. From Inner Charleston
Slough, the water is currently pumped underground to the Sailing Lake. It is released into
the Lake through ports. At the southeastern end of the Lake, a weir collects the overflow
and the water is released into Permanente Creek via a series of pipes. The outflow at the
Creek is just under the vehicular bridge leading to the Rengstorff House. From Permanente
Creek, the water flows back out into the Bay.
The City began construction on the Shoreline Sailing Lake Water Supply Project in November
2005. The project consists of a new pump station by Inner Charleston Slough (ICS), two new
discharge ports into the lake, lake intake structure, 1200 feet of 42 and 997 feet
of 24 High Density Polyethylene (HDPE) pipe, 1725 feet of lake bank stabilization
and the abandonment in place of the existing distribution system that runs through Coast
Casey Forebay and under the lake. The new distribution pipeline runs in the levees to
provide accessibility for maintenance. It is sized to allow large flows back from the Lake
to the ICS to ensure the channel is scoured daily. The daily scouring will prevent
siltation from closing off water flowing from San Francisco Bay. The lake level was
lowered three feet so that work could begin on the first phase of the project which was
bank restoration. Without the new Shoreline Water Supply Project, in a few years, the
inner slough would accumulate enough silt so that pumping would be difficult, if not
impossible, and the Lake would be left without a water source.
New Range Hours
Very few people have been using the range during the last hour the facility is
now open. Especially during the winter months, low temperatures and winds in the evening
often make it uncomfortable for practice. For example, during December, an average of one
medium bucket of balls was purchased daily from 6:00 p.m. to 7:00 p.m. Effective March 1,
2006, on a trail basis, we will be implementing a new schedule: March, April and October
last ball sold at 7:00 p.m., range closes at 7:30 p.m.; November through February
last ball sold at 6:00 p.m., range closes at 6:30 p.m.; May through September
last ball sold at 8:00p.m., range closes at 8:30 p.m. The new schedule will allow
for optimum usage of the facility and still provide many opportunities for patrons to
access the facility. It will improve our energy conservation efforts. It will also allow
us to more efficiently use staff time so that we may provide better overall customer
service. We will monitor the activity at the range to insure the new hours are not
adversely affecting golfers.
Dirt Import for Spring/Summer 2006
As in the past, this spring and summer we will be importing dirt to correct sinkholes and
other low areas on the course. For 2006, we will be concentrating our efforts on Holes 18,
13 and 10. On Hole # 18, dirt will be added directly behind the green toward Permanente
Creek. The area was damaged due to work related to the underground fire we experienced
this winter. We will also be filling in the sinkhole in front of the instructional tent.
In addition, Superintendent Steve
Crane plans to add mounds in the area to discourage people from walking through the range
on their way back to the Pro Shop. At Hole #13, the approach and apron (about 50 to 75
yards away from the green) have been under water at various times over the winter season.
Fill will be added to these areas and a drain line installed to eliminate the wet spots. A
temporary green will be used for approximately one week. With work being done in front of
the green and truck hauling to the right, the temporary green will eliminate any problems
or safety issues associated with the project. At Hole #10, the old cart path (the curve as
you approach the green) will be removed. Fill will be added to the left side of the newer
cart path. Mounds will also be added with the area graded toward the Sailing Lake.
|